FEES & STAGES
Architect's fees are related to the size and function of a building (commercial / residential / warehouse) and are usually based on a percentage of the final construction cost for a project. Dependent on the size and nature of the project, this percentage can range from 7 to 18%. McCaren Design will assess each potential project and decide on the correct fee percentage to charge based on the RIBA’s indicative fee scales, we are happy to supply full details of these scales on request.

In the initial stages of a project it is often impossible to estimate the construction cost since this does not become clear until the design has been developed to a detailed level. Therefore McCaren Design usually charge an agreed lump sum figure for the preliminary stages of a project. Once the client is happy with our design proposal we are then able to determine a budget estimate for the construction costs, and will charge a percentage based fee from this point onwards.

 

PROJECT STAGES – SERVICES
Most architects work to a standard template of project stages defined by the Royal Institute of British Architects (RIBA). For guidance, a brief explanation of each stage is given below. McCaren Design will tailor their service to meet your needs whether this is on a partial service basis (eg. producing drawings for a planning application – Stage A – D only) or a full service basis (managing the contract and seeing the project through to completion – Stage A - L). The service we provide at each stage is as follows:

 TOP

TOP

Stage H  Appointment of Contractor
Having hopefully obtained a tender which is within the budget price, we would usually draw up Contract Documents that formalise the agreement between the Client and the Contractor.

Stage L  Practical Completion
When the works are satisfactorily completed a Certificate of Practical Completion is issued, this starts the 6 month Defects Liability period, during which time the Contractor is obliged to remedy any defect arising from the works.

Stage M  Final Account
At the end of this 6 month period and assuming that all outstanding defects have been rectified, a Final Certificate is issued terminating the Contract.